Windham Low Pressure Sewer System – Windham, Maine

The Solution

Windham wanted a system that would be just as reliable for its community as a traditional sewer. After extensive discussion and design, the town selected F.R. Mahony & Associates and Environment One (E/One). E/One LPS grinder pump stations were used in Phase 1 to serve the commercial area. With the help and support of F.R. Mahony and E/One, Windham successfully connected most of this area to the new system. Shaw Brothers completed the site work for the project.

Why Low Pressure Sewer

In low pressure sewer, each property has its own E/One grinder pump station that sends wastewater through small-diameter pressure pipe to the main. Because the system does not depend on grade, the piping can be installed with shallower, narrower trenches and routed around obstacles. That flexibility makes LPS a strong fit for busy commercial corridors where space is tight and disruption to businesses needs to be kept to a minimum.

Results

Phase 1 of the Windham sewer project was six years in the making. By using E/One low pressure sewer technology where gravity was difficult, the town was able to connect most of the North Windham commercial area, helping to improve local businesses and the value of their properties.

Looking Ahead

Phase 1 is the first of several phases in Windham’s move from septic to sewer. As the town continues to expand, E/One LPS may play a role in future phases. F.R. Mahony & Associates and E/One are proud to have been part of this milestone for the Town of Windham.

Download this case study

Project At A Glance – 

Location: North Windham, ME (Route 302 / Roosevelt Trail)

Customer: Town of Windham

Phase: Phase 1 of a multi-phase sewer expansion

System: E/One low pressure sewer (LPS) grinder pump stations

Treatment: Windham’s first wastewater treatment facility, built with funding and support from the Portland Water District

Site work: Shaw Brothers

Supplied by: F.R. Mahony & Associates and Environment One Corporation 

Timeline: Six years from planning to Phase 1